Platform: Workday HCM, worksheet files inside Workday, and Workday Adaptive Planning
Scope: discovery for moving the yearly reorganisation process into the planning model
The business problem
Every year end, financial analysts move workers between budget groups, departments, products and legal entities. The process ran in two large worksheet files. One person rebuilt the files each year, analysts could not work in them together, the upload to Workday was manual, and the planning model was reconciled by hand afterwards. The organisation wanted the whole process inside Workday Adaptive Planning.
Existing architecture
Analysts enter new codes against each position in the first file, and formulas validate and classify each change. A second file consolidates all entries for review and upload. In the planning model, levels load daily from Workday through a set of segment queries, a combine step, a remap step and a loader.
Why it happened
Discovery found new organisational members were being sourced indirectly through worker records, while the Workday and planning hierarchies had substantial mismatches. Hardcoded transformations masked the differences and made the intended reorganisation process difficult to support ahead of effective dates.
Design decision
We recommended fixing the foundation before building the new process, and the organisation agreed to a phased plan. Levels come first, because the business has to agree the target hierarchy. Dimensions come second, sourced from foundation reports that do not depend on workers. The reorganisation build follows on the clean base.
The existing process runs one more cycle in the worksheet files. Nothing that works today is switched off early.
Implementation approach
- Compare every level in planning with the Workday hierarchy and mark each as matched, inactive or planning-only.
- Document the transformation logic between source and loader.
- For each change scenario, list the downstream impact: a new level, a renamed parent, a deactivation, a restructure.
- Build new Workday reports that return all dimension members, with an effective date parameter.
- Switch the dimension loaders, then simplify the transformation layer.
Controls and validation
The plan keeps existing reports running in parallel while the new ones are built. The proposed migration retains prior members as inactive where required, so history stays reportable. The downstream export to the consolidation system must keep working at every step.
Outcome
The business agreed to a phased foundation-first plan, preserving the existing year-end process during transition. The level analysis and the reorganisation build come in later phases.
Lessons learned
- Check how dimension members reach the planning model before designing a process that needs new members early.
- A transformation layer that bridges two hierarchies is a sign the hierarchies should be aligned at the source.
- Saying that the foundation is not ready is a valid result of discovery.
Scope of the outcome
Foundation gaps identified and a phased approach agreed; reorganization build not asserted.
EPMLogic | Implementation insight based on an anonymized scenario. Exact operational amounts and client details are intentionally omitted.