When we first open Model Management in Workday Adaptive Planning, there is a lot on one screen.
Versions.
Time.
Levels.
Dimensions.
Accounts.
Sheets.
Rules.
Currencies.
Exchange rates.
Planning Center.
Intelligent Planning.
It is tempting to treat these as separate administration areas.
We do not look at them that way.
Model Management is where much of the structure of an Adaptive Planning application comes together. A change in one area can affect calculations, data loads, sheets, reports, security, or how users work with the model.
That is why we normally want to understand the model before changing it.
The screenshot in this article is a good example. Nothing on the screen looks particularly complicated by itself. The complexity comes from how these objects connect.
Workday describes the Modeling area as supporting custom dimensions, levels, accounts, attributes, sheets, versions, currencies, exchange rates, and rules. That matches what we see in Model Management.
The useful question is not what each menu does.
The useful question is what each part tells us about the design of the model.
We start with versions and time
The first area we normally look at is Versions and Time.
Versions tell us how the planning process has been separated.
Workday Adaptive Planning supports Actuals and Plan versions. A version represents a financial scenario, and Plan versions can hold budgeted or forecasted data. The account, level, and dimension structures remain part of the model across versions.
That sounds straightforward, but version design tells us a lot about an application.
We might find an Actuals version, an annual budget, a current forecast, and several scenario versions.
That may be exactly what the business needs.
Or we may find years of old versions, multiple copies of forecasts, test versions, and temporary scenarios that were never cleaned up.
The first question we ask is simple.
Why does each version exist?
If there is a clear answer, fine.
If nobody knows why a version exists, that is usually a sign that the model needs some housekeeping before more versions are added.
Workday supports folders for organizing Plan versions, including separating current plans, older plans, budgets, forecasts, and scenarios.
We also look at how versions are controlled.
For example, Workday supports locking a Plan version so users cannot continue editing sheet data. That can be useful when a budget or forecast needs to be preserved.
The point is not to create a complicated version strategy.
It is to make it obvious which version is current, which ones are historical, and what users are expected to do in each one.
Time is connected to this.
A budget might cover one year.
A forecast may extend beyond the current fiscal year.
A long range plan may need several future years.
Historical actuals may need to remain available for trend analysis.
We want to understand those requirements before extending the calendar or changing the planning horizon.
More time is not automatically better.
If nobody plans or reports against an old period, keeping unnecessary history available everywhere can add model size without adding much value.
Workday’s model design guidance specifically discusses managing the left scroll limit of versions as one way of reducing version size and removing irrelevant periods from sheets.
That is a small setting, but it reflects a broader architecture principle.
Keep what the planning process actually needs.
Levels tell us how the organization plans
The next area we usually look at is Levels.
Levels are important because they often represent how responsibility is organized in the model.
Depending on the implementation, that might be cost centers, departments, companies, business units, regions, or another organizational hierarchy.
The hierarchy matters because levels roll up.
It also matters for integrations.
Workday’s Planning Level Loader is designed to synchronize organizational hierarchy information from a source system into Adaptive Planning. The loader can create new levels or update existing ones from staging data.
That immediately gives us two things to think about.
First, what is the source of truth for the hierarchy?
Second, how much of that hierarchy does Adaptive Planning actually need?
We do not automatically assume that every organizational object in a source system needs to exist as a planning level.
The planning model should support the way people plan and report.
For example, if planners enter expenses by cost center and Finance reports through a regional hierarchy, the level design needs to support that process.
We also pay attention to IDs.
Names change.
A department might be renamed.
A cost center description might be updated.
Stable source identifiers are normally much safer for integration mapping than depending only on descriptions.
This becomes especially important when metadata is loaded automatically.
The screenshot also shows Level Attributes.
Attributes can help classify levels without changing the hierarchy itself.
That distinction is useful.
If the organization needs another way to group departments for reporting, that does not automatically mean another hierarchy level is required.
Sometimes an attribute is enough.
Dimensions need a business reason
Dimensions are one of the easiest places for an Adaptive Planning model to become unnecessarily complicated.
A source system can contain many fields.
Company.
Cost center.
Region.
Product.
Customer.
Project.
Location.
Channel.
Business line.
Transaction type.
That does not mean every field should become an Adaptive Planning dimension.
When we review a dimension, we ask what the business actually does with it.
Do users plan by it?
Do formulas depend on it?
Do reports need it?
Does it need to be part of a data intersection?
Does security depend on it?
If none of those apply, there should be a good reason for keeping it in the planning model.
Workday provides Planning Dimension Loaders for bringing dimension values from staging into Adaptive Planning. These loaders can update existing values and, depending on configuration, create new values found in the source.
That is useful for keeping metadata synchronized.
It also means we need to be careful about what the integration is allowed to create.
A source field with thousands of values can quickly become a large planning dimension if the architecture has not been thought through.
We normally want to answer one question before adding another dimension.
What planning problem does this solve?
If the answer is clear, the dimension probably has a place.
If the answer is simply that the field exists in the source, we would look again.
The screenshot also shows Dimension Attributes.
Just like Level Attributes, these give another way to classify metadata.
That can sometimes solve a reporting or grouping requirement without introducing another dimension into every planning intersection.
Accounts are more than a chart of accounts
The Accounts section is where another major part of the model becomes visible.
The screenshot shows General Ledger Accounts, Metric Accounts, Custom Accounts, Assumptions, Account Attributes, and Formula Validation.
These are not interchangeable.
Workday describes accounts as containers for actuals or planning data. Accounts can hold raw numbers and formulas, and account data can be used across sheets, reports, dashboards, integrations, APIs, and other parts of the application.
When we review an Adaptive Planning model, one thing we want to understand is why a value was placed in a particular account structure.
Financial actuals may naturally align with General Ledger accounts.
Operational assumptions may belong elsewhere.
Metrics may be calculated rather than loaded.
Some values may exist because they drive another calculation.
This matters because account design and formula design are closely connected.
Workday supports default formulas on several account types, including General Ledger accounts, Custom accounts, Metric accounts, calculated modeled accounts, and calculated cube accounts.
That means a change to an account is not always just a metadata change.
It may affect calculations across versions and levels.
We also pay attention to rollups.
Changing the parent of an account changes how values aggregate.
Workday documentation notes that reparenting accounts changes rollup data across versions, including locked and archived versions, although archived calculations have specific stored behavior.
That is exactly the kind of change that looks small in an administration screen but can have a much larger reporting impact.
Before moving an account, we want to understand who uses the current rollup.
Sheets show how the model is actually being used
Model Management separates Level Assigned Sheets and User Assigned Sheets.
This is where the technical model starts connecting to the user experience.
A model can be technically correct and still be painful to use.
A planner does not care how elegant the metadata structure looks if a planning sheet takes too long to open or requires entering the same information in several places.
When reviewing sheets, we normally want to understand what each sheet is responsible for.
Is it data entry?
Workforce planning?
Revenue planning?
Capital planning?
An assumptions sheet?
A detailed operational model?
A reporting support structure?
Then we look at how that sheet connects back to accounts, dimensions, levels, and versions.
The goal is not to create as few sheets as possible.
The goal is to make the purpose of each sheet clear.
If two sheets appear to solve the same problem, that is worth investigating.
If one sheet contains far more dimensional detail than the planning process requires, that is also worth investigating.
Rules depend on the model underneath them
The screenshot shows Allocation Rules and Elimination Rules.
Rules are another good example of why Model Management needs to be viewed as a connected system.
An allocation is not just a formula.
It has a source.
It has a basis.
It has targets.
Those targets exist at specific intersections of accounts, levels, versions, time, and potentially dimensions.
If those structures are unclear, allocation logic usually becomes harder to understand.
The same principle applies to other model calculations.
We prefer to understand the model first and the rule second.
Otherwise it is easy to build increasingly complicated logic to compensate for a structural problem.
Planning Center gives us evidence
Planning Center is one of the areas on this screen that we pay particular attention to when looking at model health.
Workday describes Planning Center as an area that provides insights into model functions and performance.
It includes Configuration Metrics, Report Metrics, Sheet Metrics, and Long Running Processes.
This is useful because performance discussions can easily become guesswork.
A user says the model is slow.
Someone assumes there are too many formulas.
Someone else thinks the integration is the problem.
Planning Center gives administrators data to investigate instead of guessing.
Configuration Metrics can help show how the model is changing.
Report Metrics can help with report usage and performance.
Sheet Metrics can help with sheet behavior.
Long Running Processes can show processes running for more than 30 seconds and can provide administrators with another place to investigate what is happening.
We would rather start there than immediately redesign something because one user reported that a screen felt slow.
Measure first.
Then decide what needs to change.
Intelligent Planning still depends on the basic model
The screenshot also shows Predictive Forecaster and Anomaly Detection under Intelligent Planning.
These capabilities sit inside the same Model Management area for a reason.
Predictive capability does not exist separately from the planning model.
Workday introduced Predictive Forecaster with machine learning based time series forecasting. It can use historical data and regressor data, populate selected forecast versions, and work with selected accounts and custom dimensions.
That means versions still matter.
Accounts still matter.
Dimensions still matter.
Historical data still matters.
The underlying model does not become less important because machine learning is being used.
If anything, it becomes more important to know what the model contains and what the prediction is actually being applied to.
What we try to understand before changing anything
When we look at Model Management, we are not trying to inspect every setting on the first pass.
We are trying to understand the shape of the application.
Which versions are active?
How far does the time horizon go?
What does the level hierarchy represent?
Which dimensions are genuinely used for planning?
Where do those dimensions come from?
Which accounts are loaded and which are calculated?
What is each sheet responsible for?
Which rules materially affect the results?
How is metadata maintained?
What does Planning Center tell us about the current model?
Once those questions have reasonable answers, individual configuration changes become much easier to evaluate.
A new dimension is no longer just a new dimension.
We can see which sheets it may affect.
Which integrations will need to populate it.
Which formulas may need to reference it.
Which reports may use it.
The same applies to levels, accounts, versions, and other model components.
That is the main reason we treat Model Management as an architecture area rather than an administration page.
The screen is showing the pieces.
The real work is understanding how those pieces fit together.
What we would take away from this screen
For someone learning or reviewing Workday Adaptive Planning, Model Management is one of the best places to understand the application.
Start here before jumping into individual formulas.
Understand the versions.
Understand the level hierarchy.
Look at the dimensions.
Look at the account structures.
Understand which sheets are driving the planning process.
Check the rules.
Look at Planning Center.
Then follow the integrations that maintain the model.
That gives a much better picture of how the application actually works.
A well designed Adaptive Planning model does not need to be complicated.
It needs to be understandable.
When Finance asks where a number comes from, we should be able to trace it.
When an administrator changes metadata, we should understand what else could be affected.
When a sheet slows down, we should have somewhere to start investigating.
When a new planning requirement arrives, we should know where it belongs in the existing model.
That, for us, is the real purpose of understanding Model Management.
Official Workday References
Workday Adaptive Planning Product Areas Workday documentation
Workday Adaptive Planning Versions Workday documentation
Workday Adaptive Planning Accounts Workday documentation
Workday Adaptive Planning Planning Center Workday documentation
Workday Adaptive Planning Planning Level Loader Workday documentation
Workday Adaptive Planning Planning Dimension Loader Workday documentation